Core TradesQuestion 110 of 700
Proper sequencing of roof components requires that water always flows over, not under, the layer below. Therefore drip edge at the eave and underlayment should be arranged so that:
a.Underlayment goes over the drip edge at the eave and under it at the rake
b.Drip edge is installed last on top of shingles
c.No drip edge is needed with underlayment
d.At the eave the drip edge is under the underlayment, and at the rake the drip edge is over the underlayment
Explanation
Correct sequencing puts the eave drip edge beneath the underlayment (so water on the underlayment sheds onto the drip edge and off the roof), while at the rake the drip edge goes over the underlayment. This maintains the shingle-over-lower-layer principle; the other arrangements let water get underneath.
Law Reference: 2025 CA Building Code, Chapter 15 (Roof Assemblies)Practice all 700 questions free — no signup required.
Related questions on this topic
- Counter flashing at a chimney is installed so that its top edge is embedded in or tucked into a mortar joint of the masonry, MAINLY to:
- CALCULATION: Roofing is estimated in squares (1 square = 100 square feet). A gable roof has two rectangular planes, each 40 feet by 25 feet. How many squares of roofing are needed, before waste?
- In cold climates, an ice barrier (self-adhering membrane) is applied at the eaves of a shingle roof MAINLY to:
- Continuous insulation (ci) is applied on the exterior side of the wall sheathing, over the studs, MAINLY to:
- CALCULATION: A wall assembly has three layers with R-values of R-4 (sheathing), R-13 (cavity), and R-0.68 (interior finish). Ignoring air films, what is the total nominal R-value?
- An air barrier is installed in a building envelope MAINLY to: