Core TradesQuestion 114 of 700
A water-resistive barrier (WRB) is being installed over wall sheathing. To shed water correctly, the horizontal laps must be arranged so that:
a.Upper courses tuck behind lower courses
b.All laps are sealed with tape only, in any order
c.The barrier is installed bottom to top with upper behind lower
d.Each upper course laps OVER the course below it, shingle-fashion, so water runs down the face
Explanation
A WRB must be lapped shingle-fashion with each upper course over the one below so gravity carries water down the outer face and never behind the barrier. Tucking upper behind lower, or relying on tape in the wrong order, lets water get behind the WRB.
Law Reference: 2025 CA Building Code / CRC (Weather Protection)Practice all 700 questions free — no signup required.
Related questions on this topic
- Continuous insulation (ci) is applied on the exterior side of the wall sheathing, over the studs, MAINLY to:
- CALCULATION: A wall assembly has three layers with R-values of R-4 (sheathing), R-13 (cavity), and R-0.68 (interior finish). Ignoring air films, what is the total nominal R-value?
- An air barrier is installed in a building envelope MAINLY to:
- Around a new window, the correct flashing sequence to integrate with the WRB is generally:
- Behind exterior stucco or siding, a drainage gap or weep provision is often required so that:
- Fiberglass batt insulation is compressed and stuffed tightly around wiring and into a cavity that is too shallow. The effect on thermal performance is: