Planning & EstimatingQuestion 548 of 700

During construction you find the architectural drawings show a beam at one size but the structural drawings show a larger size for the same beam. What is the BEST first action?

a.Build with the smaller architectural size to save cost
b.Submit a request for information (RFI) so the design team resolves the conflict in writing
c.Average the two sizes and proceed
d.Let the framer pick whichever is easier to install

Explanation

When contract documents conflict, the contractor should not unilaterally choose; the correct step is to submit an RFI and obtain a written clarification before building. Structural requirements usually govern member sizing, but the design professional must confirm. Option a risks an under-designed member. Option c has no engineering basis. Option d shifts a design decision to the field. Documenting the resolution protects all parties.

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report