The specifications name a specific product but add the phrase 'or equal.' A subcontractor wants to use a different brand. What is the BEST procedure?

a.Install the substitute immediately since 'or equal' allows any brand
b.Ignore the phrase and only the named product is permitted
c.Submit the proposed product for the design professional's approval before ordering
d.Let the supplier decide which product is equal

Explanation

An 'or equal' clause permits substitutions, but the burden is on the contractor to demonstrate the proposed item meets the specified performance, and the design professional must approve it before it is ordered or installed. Option a skips required approval. Option b ignores the clause. Option d improperly delegates a design judgment to a vendor. Route substitutions through the submittal and approval process.

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report