Planning & EstimatingQuestion 636 of 700
On a set of construction drawings, what is the PRIMARY purpose of a door schedule?
a.It lists the calendar dates by which each door must be installed.
b.It shows the electrical circuits feeding automatic door operators.
c.It is the closeout list of damaged doors to be replaced.
d.It is a table listing each door's mark, size, type, material, hardware, and fire rating for ordering and installation.
Explanation
Correct: a door schedule is a table keyed to door marks on the plans that gives each door's size, type, material, hardware set, and rating so it can be ordered and installed correctly. A door schedule is not a calendar of dates, an electrical drawing, or a punch list of damage; those are different documents.
Practice all 700 questions free — no signup required.
Related questions on this topic
- On a drawing at 1/4 inch = 1 foot-0 inches, a wall measures 3 inches long on the paper. What is the actual length of that wall?
- On a civil drawing using an engineer's scale of 1 inch = 20 feet, a property line measures 4.5 inches on the paper. What is its actual length, and how does an engineer's scale differ from an architect's scale?
- Which drawing type shows a building as if cut vertically to reveal interior heights, floor and wall assemblies, and how components connect?
- On construction drawings, what does a 'revision cloud' with a triangular 'delta' symbol indicate?
- Which statement BEST reflects required inspection timing for concealed work?
- During interior work, in what order must inspections generally occur before the walls are closed up?