Planning & EstimatingQuestion 639 of 700
During interior work, in what order must inspections generally occur before the walls are closed up?
a.Rough framing and rough mechanical/electrical/plumbing are inspected and approved before insulation, and insulation is inspected before drywall covers it.
b.Insulation is installed and inspected first, then rough framing, then the MEP rough-in.
c.Drywall may be hung before the rough MEP inspection to keep the schedule moving.
d.Only a single final inspection is required; the intermediate inspections are optional.
Explanation
Correct: work is inspected while still visible. Rough framing and rough MEP are approved first, then insulation is installed and inspected, and only then is drywall hung to cover everything. Installing insulation before framing/MEP approval, hanging drywall before rough MEP, or skipping intermediate inspections would conceal work that must be inspected first.
Practice all 700 questions free — no signup required.
Related questions on this topic
- On a civil drawing using an engineer's scale of 1 inch = 20 feet, a property line measures 4.5 inches on the paper. What is its actual length, and how does an engineer's scale differ from an architect's scale?
- Which drawing type shows a building as if cut vertically to reveal interior heights, floor and wall assemblies, and how components connect?
- On a set of construction drawings, what is the PRIMARY purpose of a door schedule?
- On construction drawings, what does a 'revision cloud' with a triangular 'delta' symbol indicate?
- Which statement BEST reflects required inspection timing for concealed work?
- In critical path method (CPM) scheduling, which statement is correct?