Contracts & ExecutionQuestion 188 of 690
On a fixed-price contract, the contractor's estimate was $100,000 but actual costs reached $112,000. The owner still pays only the agreed price. The contractor's profit or loss is:
a.A $12,000 profit
b.A $12,000 loss
c.Break-even, no profit or loss
d.Determined later by the owner
Explanation
In a fixed-price contract the price is locked. With costs of $112,000 and revenue of $100,000, the contractor absorbs a $12,000 loss; cost-risk falls entirely on the contractor.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor estimates a job will take 320 labor hours at a fully burdened rate of $55 per hour. What is the estimated labor cost?
- Three contractors submit sealed bids of $182,000, $176,500, and $189,300 for the same defined scope. The lowest responsible, responsive bid is:
- A general contractor uses a critical path method (CPM) schedule mainly to:
- If a contractor performs home improvement work without a written contract or with a noncompliant contract, the most likely consequence is:
- An owner asks a contractor to add an unforeseen scope of work mid-project. To be paid for the extra work, the contractor should FIRST:
- California prompt payment laws are designed primarily to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review