Contracts & ExecutionQuestion 186 of 690
Three contractors submit sealed bids of $182,000, $176,500, and $189,300 for the same defined scope. The lowest responsible, responsive bid is:
a.$176,500
b.$189,300
c.$182,000
d.The average of the three bids
Explanation
Competitive bidding awards the contract to the lowest responsible and responsive bidder. Among $182,000, $176,500, and $189,300, the lowest is $176,500.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor signs a $700 repair contract with a homeowner. Which statement is correct?
- A contractor's bid totals $90,000, of which $54,000 is direct cost. What percentage of the bid is gross profit and overhead combined?
- A contractor estimates a job will take 320 labor hours at a fully burdened rate of $55 per hour. What is the estimated labor cost?
- A general contractor uses a critical path method (CPM) schedule mainly to:
- On a fixed-price contract, the contractor's estimate was $100,000 but actual costs reached $112,000. The owner still pays only the agreed price. The contractor's profit or loss is:
- If a contractor performs home improvement work without a written contract or with a noncompliant contract, the most likely consequence is: