Contracts & ExecutionQuestion 190 of 690
An owner asks a contractor to add an unforeseen scope of work mid-project. To be paid for the extra work, the contractor should FIRST:
a.Get a written, signed change order describing the added work and its price before performing it
b.Complete the extra work and bill it on the final invoice as a surprise
c.Stop all work until the owner pays cash up front
d.Report the owner to the CSLB
Explanation
Extra or changed work should be authorized by a written change order signed by both parties before it is performed, so the price and scope are clear and the contractor's right to payment is protected.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A general contractor uses a critical path method (CPM) schedule mainly to:
- On a fixed-price contract, the contractor's estimate was $100,000 but actual costs reached $112,000. The owner still pays only the agreed price. The contractor's profit or loss is:
- If a contractor performs home improvement work without a written contract or with a noncompliant contract, the most likely consequence is:
- California prompt payment laws are designed primarily to:
- A contractor wishes to require a larger down payment than the law allows because a custom-ordered material must be paid for up front. The proper way to handle this is to:
- A contractor's overhead is best described as:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review