A subcontractor prepares a mechanics' lien claim. Which of the following items is REQUIRED on the face of the lien?
Explanation
§8416(a) lists what a claim of mechanics lien must contain, and every item is about the claim itself: a statement of the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant or to whom it furnished work, a description of the site sufficient for identification, the claimant's address, a completed proof of service affidavit, and the NOTICE OF MECHANICS LIEN in at least 10-point boldface type — the whole statement signed and verified by the claimant. Nothing in it calls for the owner's loan details, so (a) is invented; nothing calls for other subcontractors' licence numbers, which is (b); and the contract is evidence rather than a lien requirement, which is (c). §8410 is the separate condition that trips claimants up: a lien is enforceable only where the preliminary notice was given and proof of it made.
Law Reference: Civil Code §8416(a); §8410This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An architect prepared plans for a project that the owner ultimately decided not to build, and the architect's fees went unpaid. Under California law, the architect may record a special lien against the property known as a:
- On a California public works project, a second-tier supplier was not paid by the subcontractor. Because no mechanics' lien can attach to public property, the supplier's primary recovery vehicle is generally:
- Which statement BEST captures the practical difference between a mechanics' lien and a stop payment notice on a private project?
- A subcontractor records a mechanics' lien but fails to serve a copy of the lien (with the required proof of service affidavit) on the owner. Under California's strict-compliance rule, the most likely consequence is that the lien:
- On a private project where no Notice of Completion is recorded, a subcontractor who served a proper preliminary notice must generally serve a stop payment notice on the construction lender within:
- A subcontractor on a private residential remodel wishes to preserve mechanics' lien rights. The preliminary 20-day notice under Civil Code §8200 must be served:
Last reviewed: · editorial process