Insurance & LiensQuestion 641 of 690
After recording a mechanics' lien on a private project, a claimant must file an action to enforce (foreclose) the lien within:
a.90 days after the lien was recorded, or the lien becomes unenforceable
b.180 days after recording, with two 90-day extensions allowed
c.1 year after the contract was awarded
d.4 years, per the contract statute of limitations
Explanation
Civil Code §8460 requires a claimant to commence an action to enforce a recorded mechanics' lien within 90 days after the lien is recorded; otherwise the lien expires and is unenforceable. The claimant and owner may extend the deadline by written agreement under §8460(b), but only to up to one year from completion. The 180-day option does not exist. The 1-year-from-award and 4-year statute options confuse breach-of-written-contract limitations with the much shorter mechanics'-lien deadline. Missing this 90-day window is one of the most common ways subcontractors lose lien rights.
Law Reference: Civil Code §8460Practice all 690 questions free — no signup required.
Related questions on this topic
- On a private project where no Notice of Completion is recorded, a subcontractor who served a proper preliminary notice must generally serve a stop payment notice on the construction lender within:
- A subcontractor on a private residential remodel wishes to preserve mechanics' lien rights. The preliminary 20-day notice under Civil Code §8200 must be served:
- On a private work of improvement, a direct (prime) contractor must record a mechanics' lien within how many days after completion of the work, when no notice of completion or cessation has been recorded?
- Under Labor Code §3700, a California contractor that has even one employee must:
- A licensed contractor with no employees has filed an Exemption from Workers' Compensation with the CSLB. The contractor then hires an employee. Under Bus. & Prof. Code §7125 and §7125.4, what must the contractor do?
- A material supplier delivers $40,000 of lumber to a private construction project on July 1. To fully preserve mechanics' lien, stop payment notice, AND payment bond claim rights, the supplier must serve a preliminary notice under Civil Code §8200 on the owner, direct contractor, and construction lender no later than:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review