On a private works contract entered into on or after January 1, 2026, how much retention may be withheld from each payment?
Explanation
Civil Code §8811, added by SB 61 and operative for contracts entered into on or after January 1, 2026, caps retention on a private work of improvement at 5 percent — of each payment and of the contract price — at every tier: owner to direct contractor, direct contractor to subcontractor, and below (b). The two exceptions behind the word 'narrow' are a residential project that is not mixed use and does not exceed four stories, and a subcontractor that fails to furnish a performance and payment bond from an admitted surety after written notice given at or before bid time. The prevailing party in an action to enforce the section recovers attorney's fees. (a) states the law as it stood before 2026, when private retention really was a pure matter of contract. (c) is the 10 percent custom the statute was passed to end; it now survives only inside those two exceptions and on contracts signed before 2026. (d) has the right figure but the wrong scope — Public Contract Code §7201 has capped most state and local public works at 5 percent for years, and §8811 extends the same ceiling to private work.
Law Reference: Civil Code §8811; Public Contract Code §7201This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- Instead of filing a contractor's license bond, a licensee may deposit cash or equivalent securities with the State Treasurer under Bus. & Prof. Code §7071.12. To replace the $25,000 license bond entirely with cash, the licensee must deposit:
- A Responsible Managing Employee (RME) differs from a Responsible Managing Officer (RMO) in that an RME must:
- A general contractor classifies its on-site framer as an independent contractor and issues a 1099-NEC instead of a W-2. If the framer is later determined to be a W-2 employee under AB-5 and federal common-law tests, the general contractor will likely be liable for:
- Effective January 1, 2023, the California Contractor License Bond was increased to:
- When is a Bond of Qualifying Individual (BQI) required, separate from the standard $25,000 Contractor License Bond?
- A contractor's direct job costs are $8,000. He applies a 25% markup on cost. What is the total price he charges the customer?
Last reviewed: · editorial process