Business FinancesQuestion 663 of 1605

On a private construction project, the owner is generally entitled to withhold from each progress payment a 'retention' (retainage) of up to:

a.Whatever the lender requires, with no statutory ceiling on public projects
b.An amount as agreed in the contract, but customarily 5%–10% on private work; for public works on most state contracts, retention is capped at 5% under Public Contract Code §7201
c.20% during the first half of the project and 0% thereafter
d.10% by statute, with no contract flexibility

Explanation

On private works, retention amounts are a matter of contract — typically 5%–10% — while Public Contract Code §7201 caps retention on most state public works contracts at 5% (with limited exceptions for project-specific findings). Civil Code §8812 and §8814 govern timing of retention release on private projects (generally within 45 days of completion). The other options misstate the legal framework. Retention serves as performance security and a source for back charges, but excessive withholding triggers prompt-payment penalties (2% per month) and attorneys' fees under §8818.

Law Reference: Civil Code §8810

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report