Business & LicensingQuestion 1418 of 1605

A contractor breaks a $3,000 job into four separate $750 invoices to avoid the license requirement. Is this permissible?

a.Yes, each invoice is under $1,000
b.Yes, if the customer agrees
c.No, because the aggregate contract price determines whether a license is required
d.Only for home improvement work

Explanation

Under B&P Code section 7048, the exemption looks at the aggregate contract price. Dividing a larger project into smaller amounts to evade licensing is prohibited; the true total ($3,000) requires a license.

Law Reference: B&P Code §7048