Business & LicensingQuestion 1424 of 1605

A home improvement contractor may collect progress payments in what manner?

a.Payments that do not exceed the value of work performed or material delivered
b.All money up front
c.Double the value of work done
d.Only after full completion

Explanation

Under B&P Code section 7159.5, after the down payment, payments requested may not exceed the value of work performed or materials delivered. This prevents contractors from getting too far ahead of the work.

Law Reference: B&P Code §7159.5