When a contract states that 'time is of the essence,' it means:

a.The contractor may finish whenever convenient
b.Only the owner is bound by deadlines
c.Timely performance is a material term, and failure to perform on time can be treated as a material breach
d.The completion date is merely a goal with no consequences

Explanation

A 'time is of the essence' clause makes timely performance a material term of the contract. Missing the agreed deadline is then not a trivial matter but can constitute a material breach entitling the other party to remedies. Without such a clause, reasonable delays are more likely tolerated. The clause binds the performing party to the schedule and signals that dates are essential, not aspirational.

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report