Operational ProceduresCâu 75 / 100
In a formal change-management process, what should be prepared in case a change causes unexpected problems in production?
a.A louder alarm
b.A rollback (back-out) plan
c.A brighter display
d.A faster CPU
Giải thích
A rollback or back-out plan defines how to revert a change safely if it fails, minimizing downtime. It is a core part of responsible change management and unrelated to hardware upgrades or alarms.
Luyện miễn phí toàn bộ 100 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Why is it important to maintain accurate, up-to-date documentation such as network diagrams and asset inventories?
- Which safety practice protects sensitive electronic components from static discharge while a technician works inside a computer?
- According to standard change management, what must typically happen before a significant change is implemented in a production environment?
- Which document defines the acceptable ways employees may use company computers, networks, and internet access?
- When handling a customer's confidential data during a repair, which behavior best respects privacy and professional conduct?
- Which fire extinguisher class is appropriate for electrical fires involving energized equipment?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với CompTIA A+ Core 2 (220-1102) · Quy trình kiểm tra