Operational ProceduresCâu 92 / 100
Under change management, why should a change include a documented 'end-user acceptance' or verification step after implementation?
a.To increase RAM automatically
b.To disable logging
c.To confirm the change works as intended and the issue is resolved
d.To overclock the GPU
Giải thích
Verifying end-user acceptance confirms the change achieved its goal and did not introduce new problems before the change is closed. It does not alter hardware or logging by itself.
Luyện miễn phí toàn bộ 100 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Which basic scripting construct repeats a block of instructions until a condition is met, and is fundamental to automation?
- When a customer becomes upset during a support interaction, which professional communication practice is most appropriate?
- Which purpose does a 'bill of materials' (BOM) or asset inventory serve in IT operations?
- Which environmental and safety consideration applies when using compressed air to clean dust from a computer?
- What is the main benefit of following a standardized incident-response and documentation procedure during a security event?
- When disposing of old electronics, which approach aligns with environmental regulations and responsible practice?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với CompTIA A+ Core 2 (220-1102) · Quy trình kiểm tra