When placing concrete in cold weather, the MOST important protective measure is to:
a.Keep the concrete above freezing until it has gained adequate early strength
b.Add extra water to keep the mix workable in the cold
c.Remove all curing blankets as soon as finishing is complete
d.Increase the slump to speed up placement
Giải thích
Fresh concrete must be kept above freezing until it develops enough early strength, because water freezing in the paste disrupts hydration and permanently weakens it. Adding water or increasing slump raises the water-to-cement ratio and lowers strength, and removing insulation early exposes the concrete to freezing.
Trích dẫn luật: 2025 CA Building Code, Chapter 19 (Concrete)Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A driveway slab measures 24 ft by 30 ft and is 4 inches thick. Approximately how many cubic yards of concrete are required (no waste allowance)?
- For typical residential foundations in a moderate weathering region, what is a common MINIMUM specified 28-day compressive strength for the concrete?
- A continuous foundation footing is 18 inches wide, 10 inches deep, and 90 feet long. Approximately how many cubic yards of concrete does it contain?
- Tooled or sawn control (contraction) joints are placed in a concrete slab-on-grade PRIMARILY to:
- A concrete foundation wall is 8 ft tall, 40 ft long, and 8 inches thick. Approximately how many cubic yards of concrete are needed (no waste allowance)?
- Rebar chairs and bar supports are used during concrete placement PRIMARILY to:
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra