On a grading plan, a marked 'cut and fill' stake set by the surveyor PRIMARILY tells the operator:
a.The property boundary line
b.The location of underground utilities
c.How much to excavate (cut) or add (fill) to reach the design grade at that point
d.The maximum allowable slope of the finished lot
Giải thích
A cut-and-fill stake indicates how far the existing ground is above or below the design grade, telling the operator how much soil to remove or add at that station. It is not a boundary marker, a utility locator, or a statement of maximum slope.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A radiant barrier installed in an attic reduces summer heat gain PRIMARILY by:
- A wall assembly has a total thermal resistance of R-20. What is its approximate overall U-factor (heat-transfer coefficient)?
- A trench measures 90 ft long, 3 ft wide, and 4 ft deep. How many bank (in-place) cubic yards of soil must be excavated?
- A Proctor compaction test is performed on a soil PRIMARILY to determine its:
- To drain surface water away from a building, finished grade should generally fall a MINIMUM of how much within the first 10 feet from the foundation?
- A sewer line drops 2.5 feet in elevation over a horizontal length of 250 feet. What is the slope expressed as a percentage?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra