Framing & StructuralCâu 390 / 700
When prefabricated wood roof trusses are delivered to a jobsite, which practice BEST preserves their engineered performance?
a.Install them only per the truss manufacturer's engineered layout and bracing plan
b.Field-cut chords or webs as needed to fit obstructions
c.Notch the bottom chord to run plumbing without approval
d.Store them flat-stacked in mud until installation
Giải thích
Trusses are engineered assemblies that must be installed and braced exactly per the manufacturer's layout and bracing design. Field-cutting chords or webs, notching the bottom chord, or storing them improperly all compromise the engineered load path and can void the design and cause failure.
Trích dẫn luật: 2025 CA Residential Code §R802.3Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- To resist lateral separation of an exterior wood deck from the dwelling during seismic or live loads, which connection is the BEST practice at the ledger-to-band-joist interface?
- How many board feet are contained in ten framing members that are each 2 inches thick, 6 inches wide, and 12 feet long?
- In high-wind and seismic regions, what is the MAIN purpose of installing metal framing anchors (hurricane or seismic ties) connecting each rafter or truss to the top plate?
- What is the MINIMUM headroom clearance required over a residential stairway, measured vertically from the tread nosing line?
- What is the MINIMUM clear width required above the handrail for an interior residential stairway?
- Guards required on decks and balconies must have intermediate rails or ornamental patterns such that a sphere of what MAXIMUM diameter cannot pass through the openings?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra