Planning & EstimatingCâu 487 / 700
During plan review of a two-story dwelling, you find the open side of an interior stair landing 40 inches above the floor below has no guard shown. What is the BEST action before construction proceeds?
a.Nothing, guards are only required on exterior decks
b.Ignore it because the framer will add one in the field
c.Flag it and require the plans be corrected to show a compliant guard, since the walking surface is more than 30 inches above the floor below
d.Wait until the final inspection to raise the issue
Giải thích
The Residential Code requires guards where a walking surface is more than 30 inches above the floor or grade below; 40 inches exceeds that trigger, so a guard must be shown. The BEST practice is to correct the plans before building to avoid rework and a failed inspection. Options a and b are wrong because the guard is code-required regardless of location and should not be left to chance. Option d invites costly late-stage rework.
Trích dẫn luật: 2025 California Residential CodeLuyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A cylindrical concrete pier is 3 ft in diameter and 12 ft deep. Using pi = 3.1416, what is the MINIMUM volume of concrete required to fill it?
- You need to order 15 pieces of dimensional lumber, each a 2x10 that is 20 ft long. What is the total board footage for this order?
- A rectangular room measures 12 ft by 15 ft with an 8 ft ceiling. Ignoring openings, what is the gross wall area to be painted?
- A continuous concrete footing is 18 inches wide, 12 inches deep, and 120 ft long. How many cubic yards of concrete are needed?
- A roof has 1,800 square feet of surface. Adding 10 percent for waste, how many roofing squares should be ordered (1 square = 100 sq ft)?
- A crew of 4 workers completes a task in 6 working days at 8 hours per day. At a fully burdened rate of $45 per hour, what is the estimated labor cost?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra