Planning & EstimatingCâu 603 / 700
A slab-on-grade is 20 ft by 30 ft and 4 inches thick, with a thickened (turndown) edge around the full perimeter that adds a beam 12 in wide by 12 in deep below the slab. What is the APPROXIMATE total concrete volume?
a.7.4 cubic yards
b.22 cubic yards
c.11 cubic yards
d.300 cubic yards
Giải thích
Slab field: 20 x 30 = 600 sq ft x (4 in = 0.333 ft) = 200 cubic feet. Turndown edge: perimeter = 2 x (20 + 30) = 100 ft, extra section 1 ft x 1 ft = 1 sq ft, so 100 x 1 = 100 cubic feet. Total = 300 cubic feet. Divide by 27: 300 / 27 = 11.1, about 11 cubic yards (c). Option (a) counts the slab only and omits the thickened edge. Option (b) roughly doubles the correct value. Option (d) leaves cubic feet without dividing by 27.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A footing has 3 continuous #4 rebars, each running 120 ft. Using #4 bar at about 0.668 pounds per linear foot, what is the APPROXIMATE total weight of steel?
- A CMU wall requires 450 blocks. Using a rule of about 3 bags of mortar per 100 blocks, what is the MINIMUM number of mortar bags to order?
- A common rafter has a horizontal run of 15 ft on a roof with a 5-in-12 slope (5 inches of rise per 12 inches of run). Ignoring overhang, what is the APPROXIMATE rafter length from ridge to top plate?
- An excavation is 20 ft by 30 ft and 5 ft deep. After digging, the soil swells 25 percent for hauling. APPROXIMATELY how many loose cubic yards must be hauled away?
- A wall is 9 ft high and 40 ft long and will be covered with 4x8 sheathing panels. Ignoring openings, what is the MINIMUM number of full sheets (round up)?
- When preparing a material takeoff, why does an estimator add a waste/allowance factor to the net measured quantities?