While excavating a trench, the crew is piling the removed dirt (spoil) beside the opening. What is the minimum distance the spoil pile must be kept back from the edge of the trench?
a.6 inches
b.1 foot
c.2 feet
d.It may be placed right at the edge if compacted
Giải thích
Title 8 §1541.1 requires spoil, tools, and other materials to be kept at least 2 feet from the trench edge, or restrained by a retaining device. Material stacked at the lip adds surcharge load that can trigger a cave-in and can roll back onto workers below. The 2-foot setback also keeps loose material from falling in.
Trích dẫn luật: Cal/OSHA Title 8 §1541Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A plumber is digging a trench to reach a broken sewer main. At what excavation depth does Cal/OSHA first require a protective system such as sloping, shoring, or a trench shield to guard against cave-ins?
- Cal/OSHA requires that a 'competent person' oversee trenching operations. What best describes this person's authority on the jobsite?
- A plumber is working in a trench 5 feet deep and 60 feet long installing pipe. Cal/OSHA requires a means of egress (ladder, ramp, or steps). How far must a worker ever have to travel laterally to reach that egress?
- A very deep sewer excavation reaches 22 feet. What does Cal/OSHA require regarding the protective system for a trench deeper than 20 feet?
- A crew chooses to slope the walls of a trench instead of shoring it. The soil has been classified as Type C (the least stable, such as loose sand or wet soil). What is the maximum allowable slope for Type C soil?
- Cal/OSHA recognizes several methods of protecting workers from trench cave-ins. Which of the following is a recognized protective method?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra