An toànCâu 326 / 360

Before a plumbing contractor begins excavating for a new sewer lateral, California law requires a step to avoid striking buried utilities. What must the contractor do?

a.Contact the regional one-call center (DigAlert/USA North, dial 811) and wait for utilities to be marked
b.Dig quickly at night when there is less traffic
c.Rely on the homeowner's memory of where lines run
d.Only worry about gas lines, not water or electric

Giải thích

California Government Code §4216 (the 'Dig Alert' law) requires an excavator to notify the regional notification center (call 811) at least two working days before digging so utility operators can mark their underground facilities. Striking a gas, electric, or fiber line can be deadly and costly. Hand-digging (potholing) is required near marked lines to expose them safely.

Trích dẫn luật: California Government Code §4216

Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra
Báo lỗi