A plumbing crew works all day at a remote new-construction site with no permanent facilities. What sanitation must the employer provide under Cal/OSHA?
a.Nothing until the building is finished
b.Only bottled water, no toilets
c.Workers must drive to a gas station for all needs
d.Potable drinking water and toilet facilities, plus handwashing facilities on the site
Giải thích
Under Title 8 §1526 (construction sanitation), employers must provide an adequate supply of potable drinking water, toilet facilities, and handwashing facilities at the jobsite. Plumbers handle sewage and contaminated water, so handwashing before eating or drinking is essential to prevent illness. Non-potable water sources must be clearly marked so they are never used for drinking.
Trích dẫn luật: Cal/OSHA Title 8 §1524, §1526, §1527Luyện miễn phí toàn bộ 360 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A plumber is replacing old galvanized and brass fixtures in a home built in the 1950s and notices old lead-based solder and possible lead pipe. What awareness does Cal/OSHA require?
- A plumber must cut into old cement pipe that may be asbestos-cement (transite). What is the correct precaution regarding asbestos?
- During a remodel, a plumber suspects material to be removed contains asbestos. Beyond wetting and work practices, what broader requirement often applies to asbestos removal in California?
- A plumber sets a straight (extension) ladder to reach a roof to service a vent. How should the ladder be positioned for safe use?
- A plumber must work at an elevated edge where guardrails are not feasible and uses a personal fall arrest system. What are the essential components of that system?
- A plumber must move a heavy cast-iron water heater and lengths of pipe across a jobsite. What is the safest material-handling practice?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB C-36 Plumbing Trade Examination · Quy trình kiểm tra