A contractor breaks a $3,000 job into four separate $750 invoices to avoid the license requirement. Is this permissible?
a.Yes, each invoice is under $1,000
b.Yes, if the customer agrees
c.No, because the aggregate contract price determines whether a license is required
d.Only for home improvement work
Giải thích
Under B&P Code section 7048, the exemption looks at the aggregate contract price. Dividing a larger project into smaller amounts to evade licensing is prohibited; the true total ($3,000) requires a license.
Trích dẫn luật: B&P Code §7048Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A General Building (Class B) contractor takes a project requiring framing, roofing, plumbing, and electrical. To perform trades outside its own forces, what must the Class B contractor do?
- The CSLB's Statewide Investigative Fraud Team (SWIFT) targets which conduct?
- A homeowner hires an unlicensed handyman for a $900 repair that is casual and complete in itself. Is a license required?
- When forming a joint venture to bid a large project, what licensing does the joint venture need?
- Two licensed contractors want to jointly bid and perform one large project. What does the license law require of them?
- A consumer is harmed by a licensed contractor's abandonment of a job. Which financial protection may the consumer make a claim against?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)