Drainage, Waste & VentCâu 14 / 120
A 4 in horizontal building drain runs 340 ft under a warehouse slab. Not counting the cleanout at the upstream end of the run, what is the minimum number of additional cleanouts required for spacing alone?
a.2
b.3
c.4
d.6
Giải thích
Horizontal drainage lines 4 in and smaller require a cleanout at intervals not exceeding 100 ft, so a 340 ft run needs cleanouts at roughly 100, 200, 300 ft and at the far end, which is 3 additional cleanouts beyond the upstream one to keep every interval at or under 100 ft. Two cleanouts would leave intervals longer than 100 ft, while 4 and 6 exceed the minimum the spacing rule requires.
Trích dẫn luật: UPC §708.3.3Luyện miễn phí toàn bộ 120 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A vent terminal must be located away from an openable window. Which arrangement satisfies the code?
- Which fitting is acceptable for changing direction from horizontal to vertical in a drainage line?
- Which fitting is required to change direction from horizontal to horizontal in a drainage line?
- A cleanout is installed on a 2 in horizontal waste line in a finished room. What is the minimum clearance required in front of the cleanout?
- A 6 in horizontal drainage line requires a cleanout. What is the minimum size of the cleanout opening?
- Under the UPC, where does the building drain end and the building sewer begin?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với Journeyman Plumber Licensing Exam (UPC/IPC-based) · Quy trình kiểm tra