Fixtures & Water HeatersCâu 73 / 120
Where an enclosure takes combustion air from an adjacent room through two permanent openings, where must those openings be located?
a.Both within 12 inches of the ceiling of the enclosure
b.Both within 12 inches of the floor of the enclosure
c.One at the ceiling and one at any convenient height on an outside wall
d.One within 12 inches of the top of the enclosure and one within 12 inches of the bottom
Giải thích
The two-opening method requires one opening within 12 inches of the top and one within 12 inches of the bottom of the enclosure so that heated air can exhaust high while replacement air enters low. Placing both openings high or both low defeats the convective loop that drives the air exchange. Locating the lower opening at any convenient height does not satisfy the 12 inch dimension.
Luyện miễn phí toàn bộ 120 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The same gas water heater is installed in that garage on a concrete slab. What is the minimum height that the source of ignition must be elevated above the garage floor?
- A 120,000 Btu/h gas water heater draws all of its combustion air directly from outdoors through two vertical ducts. Using the 1 square inch per 4,000 Btu/h rule for vertical ducts, what is the required free area of each opening?
- A 100,000 Btu/h water heater is placed in a closet and will take combustion air from inside the building only. Using the rule of thumb of 50 cubic feet of room volume per 1,000 Btu/h, what minimum volume of communicating space is needed?
- A shower compartment is framed 32 inches by 32 inches inside the finished walls. Does it meet the minimum area and minimum dimension requirements for a shower?
- An indirect waste pipe from a commercial ice machine is 1-1/2 inches in diameter and discharges into a floor sink. What is the minimum required air gap?
- A 3/8 inch indirect waste tube from a beverage dispenser discharges over an open receptor. Applying the air gap rule, what is the required air gap?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với Journeyman Plumber Licensing Exam (UPC/IPC-based) · Quy trình kiểm tra