During electrical construction, a rough-in (rough) inspection is generally performed:
a.After energizing the system
b.Before wiring is concealed or covered
c.Only at final occupancy
d.After the final inspection
Giải thích
The rough inspection occurs after wiring is installed but before walls or wiring are covered, so the inspector can verify concealed work.
Luyện miễn phí toàn bộ 110 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Which standard governs electrical safety-related work practices, including arc-flash and shock protection?
- Under safe electrical work practices, what is the preferred condition before working on or near exposed conductors?
- What is the primary purpose of a lockout/tagout (LOTO) procedure under Cal/OSHA?
- Who is responsible for interpreting and enforcing the requirements of the NEC?
- The NEC generally does not cover which of the following installations?
- Service equipment (other than dwellings) must be field marked with what value related to fault protection?
Cập nhật gần nhất: · quy trình kiểm tra
Đội Ngũ Biên Tập PrepPass · Đối chiếu với Master Electrician Licensing Exam (NEC-based) · Quy trình kiểm tra