PE Civil — Complete Study Guide (2026) cover

学习指南 · 2026 版

PE Civil — Complete Study Guide (2026)

General civil fundamentals across all five PE Civil depth areas.

篇幅
98 页
书内练习题
120
考试事实核对于
2026年9月
文件最后更新
2026年8月
交付
PDF + EPUB · 英文 · 即时下载

购买前请阅读: This is an independent study aid, not affiliated with or endorsed by NCEES.

阅读本声明的其余部分

The PE Civil is an open-reference exam and since April 2024 is offered as five discipline-specific depth exams; this guide reviews general civil fundamentals across all five areas plus materials. Design standards and code editions change — always confirm every value against the current PE Civil Reference Handbook, the supplied design standards, and the codes in force for your exam.

关于本书

General civil fundamentals across all five PE Civil depth areas — structural, geotechnical, water resources & environmental, transportation, and construction — plus materials, worked step by step.

考试费:每次 $400,缴给 NCEES。补考要再交一次。本指南:$19.99,一次买断。

考试事实、适合谁与变化

关于这场考试本身

NCEES PE Civil Exam — 考试事实
主管机构National Council of Examiners for Engineering and Surveying (NCEES) —— 考试由 Pearson VUE 承办

来源: NCEES — PE Civil exam

题目数量80 道题

来源: NCEES — PE Civil exam

考试时限480 分钟

来源: NCEES — PE Civil exam

及格标准NCEES 未公布

我们查阅但未找到该数据的来源: NCEES — PE Civil exam

费用
  • $400 — 考试费 (NCEES, 每次考试)

来源: NCEES — PE Civil exam

考试语言NCEES 未公布

我们查阅但未找到该数据的来源: NCEES — PE Civil exam

考试事实:每一项均附来源

翻开这本书看看

三页真实内页,直接从你将下载的 PDF 渲染而来 —— 依次是一页速查、一页讲解、一道带解析的例题。没有任何一页是为了好看而重画的。

  • 速查页
    Practice Questions · PDF 第 94 页
  • 怎么讲
    Chapter 2 — Geotechnical Engineering · PDF 第 22 页
  • 一道题的完整解析
    Practice Questions · PDF 第 56 页

包含什么,不包含什么

包含

  • All five PE Civil depth areas + materials, taught with worked examples
  • Governing equations, design-standard references, and step-by-step solutions

不包含

  • 不寄送纸质书 —— 这是一份你下载后可自行打印的文件
  • 购书不含视频课程、讲师或一对一辅导 —— 站上的免费视频是另一回事
完整的包含项与不包含项

包含

  • Common traps + "what the PE tests here" for every area
  • 120 practice questions printed in the book, with explanations — plus 409 more free on the site
  • A condensed formula & fact cram sheet for the open-reference exam
  • PDF (print & tab it) + EPUB (phone / e-reader)

不包含

  • 不含考试报名费与考点费用,这些仍需向官方机构缴纳

目录

查看 7 个部分及各部分起始页
  1. Chapter 1 — Structural Engineering第 5 页
  2. Chapter 2 — Geotechnical Engineering第 16 页
  3. Chapter 3 — Water Resources and Environmental第 24 页
  4. Chapter 4 — Transportation Engineering第 32 页
  5. Chapter 5 — Construction Engineering and Management第 40 页
  6. Chapter 6 — Engineering Materials第 48 页
  7. Practice Questions第 55 页

取自你将下载的那份 PDF,并标明各章起始页 —— 不是在此手工录入的。

免费读完整一章

完整的一章,与电子书正文一字不差。直接在此窗口滚动阅读;无需下载,无需邮箱。

在本页直接阅读第 5 章

我们没有拿轻松的绪论充数 —— 免费章节直接翻到书里最见功力的部分,让你在考试真正难的地方检验这本书讲得好不好。

免费试读 —— 就在这里读
第 5 章 · 占考试 15% · 约 8 分钟读完
Construction Engineering and Management
向下滚动 ↓

Vocabulary Is Half the Battle

Construction engineering turns a design into a built project — on time and on budget. The PE tests CPM scheduling, earned-value cost control, earthwork and quantity take-offs, equipment production, temporary works, and jobsite safety. Most questions are short arithmetic once you know the right definition, so precise vocabulary — float, swell, EV, CPI — is genuinely half the battle. Learn the terms exactly and the numbers fall out.

5.1 CPM Scheduling and Float

The Critical Path Method models a project as a network of activities. A forward pass computes early start and early finish; a backward pass computes late finish and late start:

QuantityDefinition
Early finishEF = ES + duration
Late startLS = LF − duration
Total floatLF − EF = LS − ES
Free float(successor's ES) − (activity EF)

Total float is how long an activity can slip without pushing the project end; free float is how long it can slip without delaying any successor's early start. The critical path is the longest path through the network; its activities have zero total float, and it sets the shortest possible project duration. Shortening the project therefore means shortening critical activities. In precedence (activity-on-node) diagrams the default relationship is finish-to-start, and milestones carry zero duration. Crashing buys time by adding resources; the crash cost slope identifies the cheapest activity to accelerate:

cost slope = (crash cost − normal cost) / (normal duration − crash duration)

Worked Example 5.1 — Total float. An activity has ES = 5, duration = 4 (so EF = 9), and the schedule allows LF = 12.

  • LS = LF − duration = 12 − 4 = 8. Total float = LF − EF = 12 − 9 = 3 days (= LS − ES = 8 − 5 = 3, consistent).

Worked Example 5.2 — Cheapest to crash. Activity A: normal 10 days/$5,000, crash 7 days/$8,000. Cost slope?

  • ($8,000 − $5,000)/(10 − 7) = $3,000/3 = $1,000 per day. Crash the critical activity with the lowest such slope first.

Common traps. Crashing a non-critical activity (it saves nothing). Confusing total float with free float. Forgetting the critical path is the longest path but yields the shortest duration.

What the PE tests here. Forward/backward pass; total and free float; identifying the critical path; crash cost slope and least-cost acceleration.

5.2 Earned Value and Cost Control

Earned-value management compares three dollar figures at a moment in time:

TermMeaning
Planned value (PV)Budgeted cost of work scheduled
Earned value (EV)Budgeted cost of work actually done
Actual cost (AC)Real money spent

Two indices flag trouble, both dividing EV by a baseline:

CPI = EV/AC (cost) SPI = EV/PV (schedule)

Below 1.0 is unfavorable (over budget, or behind schedule); above 1.0 is favorable. The variances:

CV = EV − AC SV = EV − PV (negative SV = behind schedule)

Forecasting uses the CPI:

EAC = BAC / CPI

Worked Example 5.3 — Reading project health. At a checkpoint: PV = $80,000, EV = $70,000, AC = $90,000.

  • CPI = EV/AC = 70,000/90,000 = 0.78 (over budget). SPI = EV/PV = 70,000/80,000 = 0.875 (behind schedule).
  • CV = 70,000 − 90,000 = −$20,000; SV = 70,000 − 80,000 = −$10,000.

Worked Example 5.4 — Forecast at completion. Budget at completion BAC = $100,000, CPI = 0.80.

  • EAC = BAC/CPI = 100,000/0.80 = $125,000 — the project is trending $25,000 over.

Common traps. Swapping the numerator/denominator in CPI or SPI (EV is always on top). Reading a CPI below 1.0 as good. Confusing cost variance with schedule variance.

What the PE tests here. Defining PV, EV, AC; computing CPI, SPI, CV, SV; interpreting above/below 1.0; forecasting EAC from CPI.

5.3 Earthwork: Swell, Shrinkage, and Volumes

Soil changes volume as it is handled, and the exam keys on three states — bank (in place), loose (excavated/hauled), and compacted (in the fill):

Loose volume = bank × (1 + swell) Load factor = 1/(1 + swell) (loose → bank) Compacted volume = bank × (1 − shrinkage)

Excavation loosens soil, so it swells; placed fill is compacted denser than bank, so it shrinks — meaning you must excavate more bank than the neat fill volume. Roadway volumes between cross-sections use the average-end-area method:

V = [(A₁ + A₂)/2] × L / 27 (to cubic yards, with A in ft², L in ft)

which slightly overestimates versus the more exact prismoidal formula. A mass (haul) diagram plots cumulative cut-minus-fill along the alignment to balance earthwork and set haul direction.

Worked Example 5.5 — How much to excavate for a fill. A fill needs 5,000 bank-yd³ of compacted material; the soil shrinks 10%.

  • Wait — read carefully. Compacted = bank × (1 − shrinkage). We need 5,000 yd³ compacted, so bank required = 5,000 / (1 − 0.10) = 5,000/0.90 = 5,556 bank-yd³ must be excavated.

Worked Example 5.6 — Average-end-area volume. Two stations 100 ft apart have cut areas A₁ = 120 ft² and A₂ = 180 ft².

  • V = [(120 + 180)/2] × 100 / 27 = 150 × 100 / 27 = 15,000/27 = 556 yd³.

Common traps. Applying swell where shrinkage belongs (excavation swells, placed fill shrinks). Forgetting to divide by 27 for cubic yards. Using the neat fill volume as the bank excavation quantity without the shrinkage correction.

What the PE tests here. Swell/shrinkage/load-factor conversions among bank, loose, and compacted; average-end-area volumes; mass-diagram reasoning.

5.4 Concrete and Material Quantities

Quantity take-offs are unit-conversion discipline. The essential fact:

1 cubic yard = 27 cubic feet

For a slab, volume = length × width × thickness; for a round column, volume = (π/4)·D²·H. Self-weight or tonnage comes from unit weight (concrete ≈ 150 pcf, asphalt ≈ 145 pcf): a layer's weight is area × thickness × unit weight, to tons by dividing by 2,000.

Worked Example 5.7 — Slab concrete order. A slab 40 ft × 30 ft × 6 in thick.

  • Volume = 40 × 30 × 0.5 ft = 600 ft³. In yards: 600/27 = 22.2 yd³ — round up when ordering.

Worked Example 5.8 — Asphalt tonnage. A road lift 3,000 ft long, 24 ft wide, 3 in thick; asphalt 145 pcf.

  • Volume = 3,000 × 24 × 0.25 = 18,000 ft³. Weight = 18,000 × 145 = 2,610,000 lb. Tons = 2,610,000/2,000 = 1,305 tons.

Common traps. Forgetting to convert thickness from inches to feet. Dividing by the wrong factor (27 for yd³, 2,000 for tons). Losing the unit chain in a multi-step order.

What the PE tests here. Cubic-yard concrete volumes; the 27 ft³/yd³ conversion; tonnage from unit weight; multi-step quantity-to-cost chains.

5.5 Equipment Production and Compaction

Equipment output is cycles per hour times payload per cycle, adjusted for real conditions:

Production = (volume per cycle) × (60 / cycle time in min) × efficiency

A common efficiency is the 50-minute working hour (factor 50/60 ≈ 0.83), accounting for delays and breaks. Balancing a hauling fleet, the number of trucks a loader keeps busy equals truck cycle time / loading time. Field compaction is checked against the lab Proctor:

relative compaction = (field dry density / max Proctor dry density) × 100% (spec often 95%)

Roller choice matches the soil — a sheepsfoot (padfoot) roller kneads cohesive clay; vibratory smooth-drum rollers suit granular soils — and thinner lifts compact more uniformly than thick ones.

Worked Example 5.9 — Excavator production. Bucket 1.5 yd³, cycle time 0.5 min, 50-min working hour.

  • Production = 1.5 × (60/0.5) × (50/60) = 1.5 × 120 × 0.833 = 150 yd³/hr.

Worked Example 5.10 — Trucks to match a loader. Truck cycle time 20 min, loading time 4 min.

  • Trucks needed = 20/4 = 5 to keep the loader continuously busy.

Common traps. Omitting the efficiency factor. Confusing cycle time (minutes) with cycles per hour. Using field/max backwards in relative compaction. Matching a sheepsfoot roller to sand or a smooth drum to clay.

What the PE tests here. Production from cycle time and payload; efficiency factors; fleet balancing; relative compaction against the Proctor; roller-to-soil matching.

5.6 Temporary Works, Estimating, and Safety

Formwork must resist fresh concrete's lateral pressure, which at the full-liquid-head limit is:

p = γ·h (about 150·h psf)

A faster placement rate raises the pressure, because the concrete stays fluid deeper before it sets; form ties carry that pressure. Rigging follows statics — a two-leg sling's leg tension is:

T = (load/2) / sin θ (θ measured from horizontal)

so as the sling flattens (θ → 0), tension climbs steeply toward infinity. On bidding, know the two markup conventions, which the exam deliberately confuses:

Markup on cost: price = cost × (1 + m) Target margin on selling price: price = cost / (1 − m)

Contingency covers identified-but-unquantified risk; a change order formally modifies scope, price, or time. Safety is largely OSHA: excavations 5 ft or deeper generally require a protective system (sloping, shoring, or shielding); Type C soil is sloped no steeper than 1.5H:1V; a "competent person" can both identify hazards and is authorized to correct them.

Worked Example 5.11 — Sling leg tension. A 4,000 lb load hangs from a two-leg sling at θ = 30° from horizontal.

  • T = (load/2)/sin θ = (4,000/2)/sin 30° = 2,000/0.5 = 4,000 lb per leg — each leg carries the full load at 30°, a vivid warning about flat sling angles.

Worked Example 5.12 — Markup versus margin. Cost is $80,000. (a) 20% markup on cost; (b) 20% margin on selling price.

  • (a) Price = 80,000 × 1.20 = $96,000.
  • (b) Price = 80,000 / (1 − 0.20) = 80,000/0.80 = $100,000. The same "20%" gives different prices — the exam exploits exactly this.

Common traps. Treating markup-on-cost and margin-on-price as the same. Forgetting that a flatter sling angle increases leg tension. Missing that a higher placement rate raises formwork pressure. Misremembering the OSHA 5 ft trigger or the 1.5H:1V Type C slope.

What the PE tests here. Formwork pressure and placement rate; sling statics; markup versus margin; contingency and change orders; OSHA excavation depth, slope, and competent-person rules.

打开免费章节 →

购买者常问的问题

怎么拿到?

付款后下载入口立即出现在本页,链接同时发到你的邮箱。无需注册账号。

不合适怎么办?

14 天内发邮件即可全额退款,无需理由。

免费练习会取消吗?

不会。站上的每一道练习题、计时模考和免费章节都继续免费。这本书是「学」的那一半,不是把免费部分围起来的门。

更多问题 (1)
能在手机上看吗?

可以 —— EPUB 适合手机和电子书阅读器,PDF 适合打印和贴标签,两种都给你。

练习免费,为什么还要买书?

我们的练习题和计时模考一直免费 —— 网站上的东西不会因为这本书而收起来。这本 $19.99 的书是「学」的那一半:知识本身,按顺序讲清楚,存成一份属于你的文件。

  • 系统讲解 —— 每个考试部分按章节从头讲到尾,不只是题目
  • 可打印可贴标签 —— 一份适合打印的 PDF,能划重点、做批注、带到书桌前
  • 随处离线学 —— EPUB 放手机或电子书阅读器;不用 wifi,不用一堆浏览器标签
  • 全在一处 —— 章节和练习题都在同一份文件里
  • 永久归你 —— 一次 $19.99,即时下载,无订阅

完整退款政策

详细信息

PrepPass 团队 · 依据官方资料核对 NCEES PE Civil Reference Handbook / exam specifications · 我们如何核对
  • 官方来源核验(NCEES PE Civil Reference Handbook / exam specifications)
  • 409 道免费练习题
同一门考试,零头的价格
$1,000–$2,500→$19.99

PE Civil review course 要 $1,000–$2,500。这本书讲的是同一门考试 —— 同样的规则、核对到最新标准 —— 只需一次性 $19.99,永久归你。

一次购买,永久下载访问。此电子书是完整的 PE Civil (NCEES) 学习指南,含 PDF 与 EPUB。仅为教育性摘要,非专业或法律意见 —— 请始终以官方来源核实当前规定。最后更新:August 2026。