Sen Lin, PrepPass 创始人 · 依据官方资料核对 NCEES PE Civil Reference Handbook / exam specifications · 我们如何核对
PE Civil — Complete Study Guide (2026) cover
PE Civil (NCEES) · 2026 版

PE Civil — Complete Study Guide (2026)

General civil fundamentals across all five PE Civil depth areas — structural, geotechnical, water resources & environmental, transportation, and construction — plus materials, worked step by step.

同一门考试,零头的价格
$1,000–$2,500$14.99

PE Civil review course 要 $1,000–$2,500。这本书讲的是同一门考试 —— 同样的规则、核对到最新标准 —— 只需一次性 $14.99,永久归你。

购买前请阅读

This is an independent study aid, not affiliated with or endorsed by NCEES. The PE Civil is an open-reference exam and since April 2024 is offered as five discipline-specific depth exams; this guide reviews general civil fundamentals across all five areas plus materials. Design standards and code editions change — always confirm every value against the current PE Civil Reference Handbook, the supplied design standards, and the codes in force for your exam.

拥有整本书 — PDF + EPUB

练习题和计时模考永远免费。这本书是「学」的那一半:

  • 逐章系统讲解——每个考试章节按顺序讲透,不只是刷题
  • 可打印、贴标签——一本能划重点、做标记的纸质参考书
  • 离线可用——PDF 用来打印,EPUB 放进手机或阅读器
  • 全部在一个文件里——章节、速记卡和练习题都在一处
$14.99一次买断 · 永久下载 · 无订阅

14 天退款保证——不满意?发邮件即可全额退款,无需理由。 退款政策

本页可免费阅读第 1 章——先读后买。一次付款解锁整本书(PDF + EPUB · 带解析练习题 · 每章速记卡)。

即时下载 PDF + EPUB · 一次买断,永久归你 · 无订阅 · 14 天退款保证 · 还没决定? 在下方免费阅读完整一章

  • 官方来源核验(NCEES PE Civil Reference Handbook / exam specifications)
  • 409 道免费练习题
  • 即时下载,永久拥有
第 5 章 —— 免费在此阅读

完整的一章,与电子书正文一字不差。直接在此窗口滚动阅读;无需下载,无需邮箱。

我们没有拿轻松的绪论充数 —— 免费章节直接翻到书里最见功力的部分,让你在考试真正难的地方检验这本书讲得好不好。

免费试读 —— 就在这里读
第 5 章 · 占考试 15% · 约 8 分钟读完
Construction Engineering and Management
向下滚动 ↓

Vocabulary Is Half the Battle

Construction engineering turns a design into a built project — on time and on budget. The PE tests CPM scheduling, earned-value cost control, earthwork and quantity take-offs, equipment production, temporary works, and jobsite safety. Most questions are short arithmetic once you know the right definition, so precise vocabulary — float, swell, EV, CPI — is genuinely half the battle. Learn the terms exactly and the numbers fall out.

5.1 CPM Scheduling and Float

The Critical Path Method models a project as a network of activities. A forward pass computes early start and early finish; a backward pass computes late finish and late start:

QuantityDefinition
Early finishEF = ES + duration
Late startLS = LF − duration
Total floatLF − EF = LS − ES
Free float(successor's ES) − (activity EF)

Total float is how long an activity can slip without pushing the project end; free float is how long it can slip without delaying any successor's early start. The critical path is the longest path through the network; its activities have zero total float, and it sets the shortest possible project duration. Shortening the project therefore means shortening critical activities. In precedence (activity-on-node) diagrams the default relationship is finish-to-start, and milestones carry zero duration. Crashing buys time by adding resources; the crash cost slope identifies the cheapest activity to accelerate:

cost slope = (crash cost − normal cost) / (normal duration − crash duration)

Worked Example 5.1 — Total float. An activity has ES = 5, duration = 4 (so EF = 9), and the schedule allows LF = 12.

  • LS = LF − duration = 12 − 4 = 8. Total float = LF − EF = 12 − 9 = 3 days (= LS − ES = 8 − 5 = 3, consistent).

Worked Example 5.2 — Cheapest to crash. Activity A: normal 10 days/$5,000, crash 7 days/$8,000. Cost slope?

  • ($8,000 − $5,000)/(10 − 7) = $3,000/3 = $1,000 per day. Crash the critical activity with the lowest such slope first.

Common traps. Crashing a non-critical activity (it saves nothing). Confusing total float with free float. Forgetting the critical path is the longest path but yields the shortest duration.

What the PE tests here. Forward/backward pass; total and free float; identifying the critical path; crash cost slope and least-cost acceleration.

5.2 Earned Value and Cost Control

Earned-value management compares three dollar figures at a moment in time:

TermMeaning
Planned value (PV)Budgeted cost of work scheduled
Earned value (EV)Budgeted cost of work actually done
Actual cost (AC)Real money spent

Two indices flag trouble, both dividing EV by a baseline:

CPI = EV/AC (cost) SPI = EV/PV (schedule)

Below 1.0 is unfavorable (over budget, or behind schedule); above 1.0 is favorable. The variances:

CV = EV − AC SV = EV − PV (negative SV = behind schedule)

Forecasting uses the CPI:

EAC = BAC / CPI

Worked Example 5.3 — Reading project health. At a checkpoint: PV = $80,000, EV = $70,000, AC = $90,000.

  • CPI = EV/AC = 70,000/90,000 = 0.78 (over budget). SPI = EV/PV = 70,000/80,000 = 0.875 (behind schedule).
  • CV = 70,000 − 90,000 = −$20,000; SV = 70,000 − 80,000 = −$10,000.

Worked Example 5.4 — Forecast at completion. Budget at completion BAC = $100,000, CPI = 0.80.

  • EAC = BAC/CPI = 100,000/0.80 = $125,000 — the project is trending $25,000 over.

Common traps. Swapping the numerator/denominator in CPI or SPI (EV is always on top). Reading a CPI below 1.0 as good. Confusing cost variance with schedule variance.

What the PE tests here. Defining PV, EV, AC; computing CPI, SPI, CV, SV; interpreting above/below 1.0; forecasting EAC from CPI.

5.3 Earthwork: Swell, Shrinkage, and Volumes

Soil changes volume as it is handled, and the exam keys on three states — bank (in place), loose (excavated/hauled), and compacted (in the fill):

Loose volume = bank × (1 + swell) Load factor = 1/(1 + swell) (loose → bank) Compacted volume = bank × (1 − shrinkage)

Excavation loosens soil, so it swells; placed fill is compacted denser than bank, so it shrinks — meaning you must excavate more bank than the neat fill volume. Roadway volumes between cross-sections use the average-end-area method:

V = [(A₁ + A₂)/2] × L / 27 (to cubic yards, with A in ft², L in ft)

which slightly overestimates versus the more exact prismoidal formula. A mass (haul) diagram plots cumulative cut-minus-fill along the alignment to balance earthwork and set haul direction.

Worked Example 5.5 — How much to excavate for a fill. A fill needs 5,000 bank-yd³ of compacted material; the soil shrinks 10%.

  • Wait — read carefully. Compacted = bank × (1 − shrinkage). We need 5,000 yd³ compacted, so bank required = 5,000 / (1 − 0.10) = 5,000/0.90 = 5,556 bank-yd³ must be excavated.

Worked Example 5.6 — Average-end-area volume. Two stations 100 ft apart have cut areas A₁ = 120 ft² and A₂ = 180 ft².

  • V = [(120 + 180)/2] × 100 / 27 = 150 × 100 / 27 = 15,000/27 = 556 yd³.

Common traps. Applying swell where shrinkage belongs (excavation swells, placed fill shrinks). Forgetting to divide by 27 for cubic yards. Using the neat fill volume as the bank excavation quantity without the shrinkage correction.

What the PE tests here. Swell/shrinkage/load-factor conversions among bank, loose, and compacted; average-end-area volumes; mass-diagram reasoning.

5.4 Concrete and Material Quantities

Quantity take-offs are unit-conversion discipline. The essential fact:

1 cubic yard = 27 cubic feet

For a slab, volume = length × width × thickness; for a round column, volume = (π/4)·D²·H. Self-weight or tonnage comes from unit weight (concrete ≈ 150 pcf, asphalt ≈ 145 pcf): a layer's weight is area × thickness × unit weight, to tons by dividing by 2,000.

Worked Example 5.7 — Slab concrete order. A slab 40 ft × 30 ft × 6 in thick.

  • Volume = 40 × 30 × 0.5 ft = 600 ft³. In yards: 600/27 = 22.2 yd³ — round up when ordering.

Worked Example 5.8 — Asphalt tonnage. A road lift 3,000 ft long, 24 ft wide, 3 in thick; asphalt 145 pcf.

  • Volume = 3,000 × 24 × 0.25 = 18,000 ft³. Weight = 18,000 × 145 = 2,610,000 lb. Tons = 2,610,000/2,000 = 1,305 tons.

Common traps. Forgetting to convert thickness from inches to feet. Dividing by the wrong factor (27 for yd³, 2,000 for tons). Losing the unit chain in a multi-step order.

What the PE tests here. Cubic-yard concrete volumes; the 27 ft³/yd³ conversion; tonnage from unit weight; multi-step quantity-to-cost chains.

5.5 Equipment Production and Compaction

Equipment output is cycles per hour times payload per cycle, adjusted for real conditions:

Production = (volume per cycle) × (60 / cycle time in min) × efficiency

A common efficiency is the 50-minute working hour (factor 50/60 ≈ 0.83), accounting for delays and breaks. Balancing a hauling fleet, the number of trucks a loader keeps busy equals truck cycle time / loading time. Field compaction is checked against the lab Proctor:

relative compaction = (field dry density / max Proctor dry density) × 100% (spec often 95%)

Roller choice matches the soil — a sheepsfoot (padfoot) roller kneads cohesive clay; vibratory smooth-drum rollers suit granular soils — and thinner lifts compact more uniformly than thick ones.

Worked Example 5.9 — Excavator production. Bucket 1.5 yd³, cycle time 0.5 min, 50-min working hour.

  • Production = 1.5 × (60/0.5) × (50/60) = 1.5 × 120 × 0.833 = 150 yd³/hr.

Worked Example 5.10 — Trucks to match a loader. Truck cycle time 20 min, loading time 4 min.

  • Trucks needed = 20/4 = 5 to keep the loader continuously busy.

Common traps. Omitting the efficiency factor. Confusing cycle time (minutes) with cycles per hour. Using field/max backwards in relative compaction. Matching a sheepsfoot roller to sand or a smooth drum to clay.

What the PE tests here. Production from cycle time and payload; efficiency factors; fleet balancing; relative compaction against the Proctor; roller-to-soil matching.

5.6 Temporary Works, Estimating, and Safety

Formwork must resist fresh concrete's lateral pressure, which at the full-liquid-head limit is:

p = γ·h (about 150·h psf)

A faster placement rate raises the pressure, because the concrete stays fluid deeper before it sets; form ties carry that pressure. Rigging follows statics — a two-leg sling's leg tension is:

T = (load/2) / sin θ (θ measured from horizontal)

so as the sling flattens (θ → 0), tension climbs steeply toward infinity. On bidding, know the two markup conventions, which the exam deliberately confuses:

Markup on cost: price = cost × (1 + m) Target margin on selling price: price = cost / (1 − m)

Contingency covers identified-but-unquantified risk; a change order formally modifies scope, price, or time. Safety is largely OSHA: excavations 5 ft or deeper generally require a protective system (sloping, shoring, or shielding); Type C soil is sloped no steeper than 1.5H:1V; a "competent person" can both identify hazards and is authorized to correct them.

Worked Example 5.11 — Sling leg tension. A 4,000 lb load hangs from a two-leg sling at θ = 30° from horizontal.

  • T = (load/2)/sin θ = (4,000/2)/sin 30° = 2,000/0.5 = 4,000 lb per leg — each leg carries the full load at 30°, a vivid warning about flat sling angles.

Worked Example 5.12 — Markup versus margin. Cost is $80,000. (a) 20% markup on cost; (b) 20% margin on selling price.

  • (a) Price = 80,000 × 1.20 = $96,000.
  • (b) Price = 80,000 / (1 − 0.20) = 80,000/0.80 = $100,000. The same "20%" gives different prices — the exam exploits exactly this.

Common traps. Treating markup-on-cost and margin-on-price as the same. Forgetting that a flatter sling angle increases leg tension. Missing that a higher placement rate raises formwork pressure. Misremembering the OSHA 5 ft trigger or the 1.5H:1V Type C slope.

What the PE tests here. Formwork pressure and placement rate; sling statics; markup versus margin; contingency and change orders; OSHA excavation depth, slope, and competent-person rules.

电子书内容

All five PE Civil depth areas + materials, taught with worked examples
Governing equations, design-standard references, and step-by-step solutions
Common traps + "what the PE tests here" for every area
120 practice questions with explanations (400+ more free on the site)
A condensed formula & fact cram sheet for the open-reference exam
PDF (print & tab it) + EPUB (phone / e-reader)

练习免费,为什么还要买书?

我们的练习题和计时模考一直免费 —— 网站上的东西不会因为这本书而收起来。这本 $14.99 的书是「学」的那一半:知识本身,按顺序讲清楚,存成一份属于你的文件。

  • 系统讲解 —— 每个考试部分按章节从头讲到尾,不只是题目
  • 可打印可贴标签 —— 一份适合打印的 PDF,能划重点、做批注、带到书桌前
  • 随处离线学 —— EPUB 放手机或电子书阅读器;不用 wifi,不用一堆浏览器标签
  • 全在一处 —— 章节、每章速记卡、练习题都在同一份文件里
  • 永久归你 —— 一次 $14.99,即时下载,无订阅

而且零风险:14 天退款保证 —— 不满意?发邮件即可全额退款,无需理由。 详见退款政策

获取电子书 —— $14.99(PDF + EPUB)↑

14 天退款保证 · 全额退款,无需理由。

一次购买,永久下载访问。此电子书是完整的 PE Civil (NCEES) 学习指南,含 PDF 与 EPUB。仅为教育性摘要,非专业或法律意见 —— 请始终以官方来源核实当前规定。最后更新:August 2026。

反馈