Contracts & ExecutionQuestion 161 of 690

On a private works project, after the owner pays the general contractor a progress payment, the general contractor must pay each subcontractor its share within how many days?

a.7 days
b.14 days
c.21 days
d.45 days

Explanation

Under California prompt payment law, a direct contractor on a private project must pay each subcontractor its portion within 7 days of receiving a progress payment from the owner.

Law Reference: Civil Code §8800

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report