Contracts & ExecutionQuestion 161 of 1605

On a private works project, after the owner pays the general contractor a progress payment, the general contractor must pay each subcontractor its share within how many days?

a.7 days
b.14 days
c.21 days
d.45 days

Explanation

Under California prompt payment law, a direct contractor on a private project must pay each subcontractor its portion within 7 days of receiving a progress payment from the owner.

Law Reference: Civil Code §8800

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report