Contracts & ExecutionQuestion 160 of 690
On a project with a $250,000 contract, the owner withholds 10% retention from each progress payment. After $150,000 of work has been billed and approved, how much retention has been withheld so far?
a.$1,500
b.$10,000
c.$15,000
d.$25,000
Explanation
Retention is withheld as a percentage of the work billed to date: 10% x $150,000 = $15,000. Retention is released after satisfactory completion, typically tied to project acceptance.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's annual overhead is $120,000 and projected annual direct job costs are $600,000. What overhead rate should be applied to each job's direct costs?
- A contractor's fixed overhead is $90,000 per year and the average gross profit margin on jobs is 30%. How much sales revenue is needed to break even on overhead?
- A contractor adds a 5% contingency to a job estimated at $200,000 in direct costs. How much money does the contingency add to the estimate?
- On a private works project, after the owner pays the general contractor a progress payment, the general contractor must pay each subcontractor its share within how many days?
- If an owner wrongfully withholds an undisputed progress payment from a general contractor, California prompt payment law allows a penalty of:
- After a project is satisfactorily completed and accepted on a private works job, the owner must release retention to the general contractor within:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review