Contracts & ExecutionQuestion 160 of 1632

On a project with a $250,000 contract, the owner withholds 5% retention from each progress payment. After $150,000 of work has been billed and approved, how much retention has been withheld so far?

a.$750
b.$12,500
c.$7,500
d.$15,000

Explanation

Retention accrues on the work billed to date, not on the contract total: 5% x $150,000 = $7,500 (c). Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026, and Public Contract Code §7201 has capped most public works at the same figure for years. (b) $12,500 applies the correct 5% to the wrong base, the full $250,000 contract, which is what will have been withheld only once everything is billed. (d) $15,000 is 10% of the billed amount — the superseded private-works custom. (a) $750 slips a decimal.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report