Contracts & ExecutionQuestion 160 of 690

On a project with a $250,000 contract, the owner withholds 10% retention from each progress payment. After $150,000 of work has been billed and approved, how much retention has been withheld so far?

a.$1,500
b.$10,000
c.$15,000
d.$25,000

Explanation

Retention is withheld as a percentage of the work billed to date: 10% x $150,000 = $15,000. Retention is released after satisfactory completion, typically tied to project acceptance.

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report