Contracts & ExecutionQuestion 157 of 690
A contractor's annual overhead is $120,000 and projected annual direct job costs are $600,000. What overhead rate should be applied to each job's direct costs?
a.20%
b.16.7%
c.5%
d.50%
Explanation
The overhead rate is total overhead divided by total direct costs: $120,000 / $600,000 = 0.20, or 20%. Each job is marked up 20% of its direct costs to recover overhead.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor wants a 30% markup on a job whose costs are $50,000. What selling price should the contractor bid?
- A contractor needs a 25% gross margin on a job. If the direct costs are $30,000, what selling price achieves that margin?
- A bid includes $60,000 in labor and materials, $12,000 in overhead, and the contractor wants $8,000 profit. What is the total bid price?
- A contractor's fixed overhead is $90,000 per year and the average gross profit margin on jobs is 30%. How much sales revenue is needed to break even on overhead?
- A contractor adds a 5% contingency to a job estimated at $200,000 in direct costs. How much money does the contingency add to the estimate?
- On a project with a $250,000 contract, the owner withholds 10% retention from each progress payment. After $150,000 of work has been billed and approved, how much retention has been withheld so far?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review