Contracts & ExecutionQuestion 182 of 690
In a cost-plus contract, the party who bears the MOST risk of cost overruns is the:
a.Owner
b.Subcontractor
c.Contractor
d.Materials supplier
Explanation
Under cost-plus, the contractor is reimbursed for actual costs plus a fee, so cost increases are passed through to the owner. The owner therefore bears the bulk of the cost-overrun risk.
Practice all 690 questions free — no signup required.
Related questions on this topic
- Under SB 800, the longest statutory standard period applies to which type of defect in new residential construction?
- Under SB 800, before a homeowner may file a construction defect lawsuit against the builder, the homeowner generally must first:
- A home improvement contract states the contract price as "to be determined" with no total dollar amount. This contract is:
- A contractor signs a $700 repair contract with a homeowner. Which statement is correct?
- A contractor's bid totals $90,000, of which $54,000 is direct cost. What percentage of the bid is gross profit and overhead combined?
- A contractor estimates a job will take 320 labor hours at a fully burdened rate of $55 per hour. What is the estimated labor cost?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review