Contracts & ExecutionQuestion 179 of 1632

Under SB 800, the longest statutory standard period applies to which type of defect in new residential construction?

a.Exterior paint and stucco
b.Interior trim and moldings
c.Major structural components
d.Cabinet and door hardware

Explanation

The structural standards carry the longest reach: Civil Code §941(a) allows an action up to 10 years after substantial completion for a violation of those standards. Paint finishes, interior trim and cabinets are fit-and-finish items, and Civil Code §900 gives them a one-year express written warranty instead, so none of the finish categories can be the longest period.

Law Reference: Civil Code §941(a); §900; §896

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report