Contracts & ExecutionQuestion 179 of 1632
Under SB 800, the longest statutory standard period applies to which type of defect in new residential construction?
a.Exterior paint and stucco
b.Interior trim and moldings
c.Major structural components
d.Cabinet and door hardware
Explanation
The structural standards carry the longest reach: Civil Code §941(a) allows an action up to 10 years after substantial completion for a violation of those standards. Paint finishes, interior trim and cabinets are fit-and-finish items, and Civil Code §900 gives them a one-year express written warranty instead, so none of the finish categories can be the longest period.
Law Reference: Civil Code §941(a); §900; §896This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A liquidated damages clause in a construction contract will most likely be unenforceable if:
- A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?
- Under California's Right to Repair Act (SB 800), the statutory standard for plumbing and electrical system defects in new residential construction generally applies for:
- Under SB 800, before a homeowner may file a construction defect lawsuit against the builder, the homeowner generally must first:
- A home improvement contract states the contract price as "to be determined" with no total dollar amount. This contract is:
- In a cost-plus contract, the party who bears the MOST risk of cost overruns is the:
Last reviewed: · editorial process
PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)