Contracts & ExecutionQuestion 177 of 690
A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?
a.$400
b.$4,800
c.$1,200
d.$12,000
Explanation
Liquidated damages accrue per day of delay: $400 x 12 days = $4,800. An enforceable clause fixes this amount in advance so actual damages need not be separately proven.
Law Reference: Civil Code §1671Practice all 690 questions free — no signup required.
Related questions on this topic
- A "punch list" near the end of a project is:
- "Substantial completion" of a construction project generally means:
- A liquidated damages clause in a construction contract will most likely be unenforceable if:
- Under California's Right to Repair Act (SB 800), the statutory standard for plumbing and electrical system defects in new residential construction generally applies for:
- Under SB 800, the longest statutory standard period applies to which type of defect in new residential construction?
- Under SB 800, before a homeowner may file a construction defect lawsuit against the builder, the homeowner generally must first:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review