Contracts & ExecutionQuestion 177 of 690

A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?

a.$400
b.$4,800
c.$1,200
d.$12,000

Explanation

Liquidated damages accrue per day of delay: $400 x 12 days = $4,800. An enforceable clause fixes this amount in advance so actual damages need not be separately proven.

Law Reference: Civil Code §1671

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report