Contracts & ExecutionQuestion 176 of 1632

A liquidated damages clause in a construction contract will most likely be unenforceable if:

a.The stated amount was unreasonable under the circumstances at signing
b.The amount is a reasonable forecast of the owner's likely loss
c.Actual damages would have been hard to calculate at the time of signing
d.Both parties negotiated the clause at arm's length with counsel

Explanation

Civil Code §1671(b) makes a liquidated damages provision valid unless the party challenging it proves the provision was unreasonable under the circumstances existing at the time the contract was made. A figure set to punish, unrelated to any harm the parties could foresee, is exactly that. The other three cut the other way: a reasonable forecast of the owner's loss is what the statute asks for, damages that were hard to quantify at signing are the classic reason to liquidate them in advance, and arm's-length bargaining with counsel makes the clause harder to attack, not easier.

Law Reference: Civil Code §1671(b)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report