Contracts & ExecutionQuestion 176 of 690
A liquidated damages clause in a construction contract will most likely be unenforceable if:
a.The stated amount bears no reasonable relationship to anticipated harm and operates as a penalty
b.The amount is a reasonable forecast of the owner's likely loss
c.Actual damages would have been hard to calculate at signing
d.Both parties negotiated the clause at arm's length
Explanation
Under Civil Code §1671, liquidated damages must be a reasonable estimate of probable harm. A clause set arbitrarily high to punish, with no relation to actual anticipated loss, is an unenforceable penalty.
Law Reference: Civil Code §1671Practice all 690 questions free — no signup required.
Related questions on this topic
- In project organization, the document that defines exactly what work is and is NOT included in a contract is the:
- A "punch list" near the end of a project is:
- "Substantial completion" of a construction project generally means:
- A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?
- Under California's Right to Repair Act (SB 800), the statutory standard for plumbing and electrical system defects in new residential construction generally applies for:
- Under SB 800, the longest statutory standard period applies to which type of defect in new residential construction?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review