Contracts & ExecutionQuestion 175 of 690
"Substantial completion" of a construction project generally means:
a.All materials have been ordered
b.The contract has been signed by both parties
c.Exactly 90% of the contract price has been paid
d.The project is complete enough for the owner to use it for its intended purpose
Explanation
Substantial completion is reached when the work is sufficiently complete that the owner can occupy or use the project for its intended purpose, even if minor punch-list items remain.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor discovers a $20,000 arithmetic error in its bid one hour after submitting it, before any contract is signed. The contractor's BEST course of action is to:
- In project organization, the document that defines exactly what work is and is NOT included in a contract is the:
- A "punch list" near the end of a project is:
- A liquidated damages clause in a construction contract will most likely be unenforceable if:
- A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?
- Under California's Right to Repair Act (SB 800), the statutory standard for plumbing and electrical system defects in new residential construction generally applies for:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review