Contracts & ExecutionQuestion 174 of 690
A "punch list" near the end of a project is:
a.A list of minor incomplete or corrective items to finish before final acceptance
b.A list of materials still to be ordered
c.The contractor's payroll records
d.A schedule of future projects
Explanation
A punch list itemizes minor defects or unfinished details that must be completed or corrected before the owner gives final acceptance and releases final payment and retention.
Practice all 690 questions free — no signup required.
Related questions on this topic
- The practice of a general contractor revealing one subcontractor's bid to a competitor to obtain a lower price is called:
- A contractor discovers a $20,000 arithmetic error in its bid one hour after submitting it, before any contract is signed. The contractor's BEST course of action is to:
- In project organization, the document that defines exactly what work is and is NOT included in a contract is the:
- "Substantial completion" of a construction project generally means:
- A liquidated damages clause in a construction contract will most likely be unenforceable if:
- A contract sets liquidated damages of $400 per day for late completion. The contractor finishes 12 days late. Assuming the clause is enforceable, how much may the owner deduct?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review