A "punch list" near the end of a project is:

a.A list of minor incomplete or corrective items to finish before final acceptance
b.A list of materials still to be ordered
c.The contractor's payroll records
d.A schedule of future projects

Explanation

A punch list itemizes minor defects or unfinished details that must be completed or corrected before the owner gives final acceptance and releases final payment and retention.