Contracts & ExecutionQuestion 173 of 690
In project organization, the document that defines exactly what work is and is NOT included in a contract is the:
a.Punch list
b.Lien release
c.Certificate of occupancy
d.Scope of work
Explanation
The scope of work spells out the specific work the contractor will perform. A clear scope prevents disputes over whether a task is included in the contract price or is extra work requiring a change order.
Practice all 690 questions free — no signup required.
Related questions on this topic
- When a general contractor relies on a subcontractor's bid to prepare its prime bid, the sub generally:
- The practice of a general contractor revealing one subcontractor's bid to a competitor to obtain a lower price is called:
- A contractor discovers a $20,000 arithmetic error in its bid one hour after submitting it, before any contract is signed. The contractor's BEST course of action is to:
- A "punch list" near the end of a project is:
- "Substantial completion" of a construction project generally means:
- A liquidated damages clause in a construction contract will most likely be unenforceable if:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review