Contracts & ExecutionQuestion 194 of 1632

On a home improvement contract, the start date and completion date provisions exist primarily to:

a.Let the contractor set the final price once work is under way
b.Start the three-day cancellation period running at the start date
c.Fix the date any retention becomes payable to the contractor
d.Give the homeowner an enforceable expectation of the project schedule

Want narrated lessons as well as practice? Learn it on the board: CSLB Law and Business · Try Chapter 2 free

Explanation

B&P §7159(d)(10) requires an 'Approximate Start Date' heading with a statement of what counts as substantial commencement of work, and §7159(d)(11) requires an 'Approximate Completion Date'. Together they give the homeowner a timeline she can hold the contractor to, and they are how a delay becomes measurable as abandonment. The price is set by the contract's price and payment-schedule terms, not by the dates. The buyer's three business days to cancel run from receipt of a signed and dated copy of the contract, not from the start date. And retention is a payment term; the date provisions do not control when it comes due.

Law Reference: B&P Code §7159(d)(10), (d)(11)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $27.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $27.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)