Contracts & ExecutionQuestion 194 of 1632

On a home improvement contract, the start date and completion date provisions exist primarily to:

a.Let the contractor set the final price once work is under way
b.Start the three-day cancellation period running at the start date
c.Fix the date any retention becomes payable to the contractor
d.Give the homeowner an enforceable expectation of the project schedule

Explanation

B&P §7159(d)(10) requires an 'Approximate Start Date' heading with a statement of what counts as substantial commencement of work, and §7159(d)(11) requires an 'Approximate Completion Date'. Together they give the homeowner a timeline she can hold the contractor to, and they are how a delay becomes measurable as abandonment. The price is set by the contract's price and payment-schedule terms, not by the dates. The buyer's three business days to cancel run from receipt of a signed and dated copy of the contract, not from the start date. And retention is a payment term; the date provisions do not control when it comes due.

Law Reference: B&P Code §7159(d)(10), (d)(11)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report