On a unit-price paving contract at $3.20 per square foot, the field measures 9,500 square feet actually paved. What is the contractor entitled to be paid?
a.$3.20
b.$30,400
c.$9,500
d.$3,040
Explanation
Under a unit-price contract, payment equals the unit price times the measured quantity: $3.20 x 9,500 sq ft = $30,400.
Practice all 690 questions free — no signup required.
Related questions on this topic
- On a home improvement contract, the start date and completion date provisions exist primarily to:
- Which item is generally considered a direct (job) cost rather than overhead?
- A contractor marks up direct costs by 35%. If the markup amount on a job is $14,000, what were the direct costs?
- A contractor finishes substantially all work on a private project and submits a proper final invoice for $30,000 (the retention). The owner refuses to pay although there is no genuine dispute. The contractor's BEST first step is to:
- An AIA-style "Application and Certificate for Payment" (commonly G702/G703) is used to:
- A contractor budgets a job at $250,000 total cost and is 60% complete. To stay on budget, total spending to date should be approximately:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review