Contracts & ExecutionQuestion 199 of 163257% of test-takers get this one wrong

An AIA-style "Application and Certificate for Payment" (commonly G702/G703) is used to:

a.Certify substantial completion and release all retention held
b.List the subcontractors and suppliers in a bid package
c.Request a progress payment against the schedule of values
d.Record a mechanics' lien claim with the county recorder

Want narrated lessons as well as practice? Learn it on the board: CSLB Law and Business · Try Chapter 2 free

Explanation

The G702 application and certificate for payment, with its G703 continuation sheet, itemizes the schedule of values and the percentage of each line item completed — that is how a progress payment is requested and certified. Substantial completion is certified on a separate form and does not by itself release retention. Subcontractor and supplier listings belong to the bid documents, not the payment application. And a mechanics' lien is a statutory claim recorded with the county, not an AIA payment form.

Law Reference: AIA G702/G703 (industry practice); Civil Code §8412 (lien recording)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $27.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $27.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)