Contracts & ExecutionQuestion 215 of 1605

Which contract type generally gives the owner the LEAST cost certainty at the time of signing?

a.Fixed-price (lump sum) contract
b.Guaranteed maximum price contract
c.Stipulated lump-sum contract
d.Cost-plus-percentage contract

Explanation

Under cost-plus-percentage, the final price is unknown until the work is done because it depends on actual costs. Fixed-price and GMP contracts give the owner far more cost certainty up front.

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report