Contracts & ExecutionQuestion 214 of 690
A contractor's bid is $120,000. After the contract is signed, the owner requests an approved change order adding $15,000 of work and a deductive change order removing $4,000. The adjusted contract price is:
a.$120,000
b.$135,000
c.$116,000
d.$131,000
Explanation
Change orders adjust the contract price up and down: $120,000 + $15,000 - $4,000 = $131,000. The adjusted price reflects all signed change orders.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor stops work on a project for two weeks because the owner has not made an undisputed progress payment that is clearly due. This work stoppage is:
- An estimate that totals all material and labor quantities from the plans, item by item, to build up a price is BEST described as:
- The home solicitation contract rules that give a three-day cancellation right apply to a contract that is:
- Which contract type generally gives the owner the LEAST cost certainty at the time of signing?
- A home improvement contract must be legible and any blank spaces should be:
- An owner-contractor agreement and a subcontract are kept consistent through:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review