Contracts & ExecutionQuestion 217 of 690
An owner-contractor agreement and a subcontract are kept consistent through:
a.Ignoring the prime contract terms entirely
b.A 'flow-down' clause that passes prime-contract obligations to the subcontractor
c.A separate license for each trade
d.A liquidated damages waiver
Explanation
A flow-down (or conduit) clause incorporates the prime contract's relevant terms into the subcontract, binding the subcontractor to the same obligations the general owes the owner for that scope.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's bid is $120,000. After the contract is signed, the owner requests an approved change order adding $15,000 of work and a deductive change order removing $4,000. The adjusted contract price is:
- Which contract type generally gives the owner the LEAST cost certainty at the time of signing?
- A home improvement contract must be legible and any blank spaces should be:
- A contractor's job-cost report shows materials are 15% over budget while labor is on budget at the 50% completion point. The contractor should:
- A subcontractor signs a CONDITIONAL waiver and release on progress payment under Civil Code §8132 in exchange for a check that later bounces. What is the legal effect on the waiver?
- A prime contractor's subcontract requires the subcontractor to indemnify the prime for ALL claims, including those arising from the prime's SOLE negligence. Under Civil Code §2782, this broad-form indemnity provision is:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review