On a construction job site, who is generally responsible for providing potable drinking water and toilet facilities for employees?
Explanation
The employer of the exposed employees provides both: 8 CCR §1524 requires an adequate supply of potable water in all places of employment, and 8 CCR §1526 requires toilets at construction jobsites - a minimum of one separate facility for each 20 employees or fraction thereof of each sex, with narrow exemptions for very small crews and for mobile crews with ready transportation. IWC Wage Order 16 §10(C) adds potable water, soap and single-use towels for hand washing. Employees cannot be left to supply their own, the project owner carries no such duty, and the general contractor's control of the site does not relieve each subcontractor of providing for its own crew.
Law Reference: 8 CCR §1524; 8 CCR §1526; IWC Wage Order 16 §10(C)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An employee is scheduled for a 12-hour shift on a construction site. How many 30-minute meal periods must the employer provide?
- An employer fails to provide a legally required meal period to an employee on a given day. What does California law require the employer to pay?
- A construction worker is scheduled to work a 6-hour shift. Under what condition may the meal period be waived?
- During a paid 10-minute rest break, an employee must be:
- An employee gives the contractor 72 hours of advance notice that they will quit. On the employee's last scheduled workday, when are final wages due?
- A contractor willfully fails to pay a discharged employee's final wages on time. The employee earned $200 per day. The waiting-time penalty under Labor Code §203 continues until paid, up to a maximum of: