An employee gives the contractor 72 hours of advance notice that they will quit. On the employee's last scheduled workday, when are final wages due?
a.Within 72 hours after the last day worked
b.By the next regular payday
c.Within 30 days of resignation
d.On the last day of work
Explanation
When an employee quits with at least 72 hours of advance notice, final wages are due on the last day of work. The 72-hour grace period only applies when the employee quits without giving such notice.
Law Reference: Labor Code §202Practice all 690 questions free — no signup required.
Related questions on this topic
- A construction worker is scheduled to work a 6-hour shift. Under what condition may the meal period be waived?
- On a construction job site, who is generally responsible for providing potable drinking water and toilet facilities for employees?
- During a paid 10-minute rest break, an employee must be:
- A contractor willfully fails to pay a discharged employee's final wages on time. The employee earned $200 per day. The waiting-time penalty under Labor Code §203 continues until paid, up to a maximum of:
- An employee earning $160 per day is discharged, and the contractor pays the final wages 8 days late without any good-faith dispute. What is the waiting-time penalty?
- A contractor lays off a worker at the end of a project. With respect to final pay, a layoff is treated the same as: