Business FinancesQuestion 51 of 690

What is the purpose of a "retainage" or "retention" clause in a construction contract?

a.To pay subcontractors before the general contractor
b.To fund project contingencies
c.To compensate the owner for delays
d.To allow the owner to withhold a portion of payment until project completion

Explanation

Retainage (typically 5–10% of each progress payment) is withheld by the owner as security until the project is substantially complete and defects are corrected. It motivates timely completion.

Law Reference: Civil Code §8812

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report