Before starting a project, a contractor should prepare a schedule of values in order to:

a.Calculate the contractor's overhead rate
b.Establish milestone payment amounts tied to completed work
c.Determine subcontractor licensing requirements
d.Set the overtime schedule for workers

Explanation

A schedule of values breaks the contract amount into line items by trade or work phase. It becomes the basis for progress payment requests (AIA G702/703), ensuring payments match completed work.