Before starting a project, a contractor should prepare a schedule of values in order to:
a.Calculate the contractor's overhead rate
b.Establish milestone payment amounts tied to completed work
c.Determine subcontractor licensing requirements
d.Set the overtime schedule for workers
Explanation
A schedule of values breaks the contract amount into line items by trade or work phase. It becomes the basis for progress payment requests (AIA G702/703), ensuring payments match completed work.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor uses the percentage-of-completion method for revenue recognition. If a job is 40% complete and the total contract value is $200,000, recognized revenue to date is:
- What is the purpose of a "retainage" or "retention" clause in a construction contract?
- A contractor's current ratio is 0.8. This means:
- A contractor receives a $5,000 deposit on a contract. Under California law for home improvement contracts, the maximum down payment is:
- Which of the following best describes "overhead" in construction estimating?
- A contractor pays an independent subcontractor $4,500 during the calendar year for installation work. Which tax form must the contractor issue to that subcontractor?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review