Before starting a project, a contractor should prepare a schedule of values in order to:

a.Calculate the contractor's annual overhead rate
b.Set milestone payments tied to the work done
c.Determine the subcontractors' licence classes
d.Set the overtime schedule for the workers

Explanation

A schedule of values divides the contract sum into line items by trade or phase, and each progress application states how complete each line is, so payment follows the work actually done. The overhead rate is computed from the company's own costs and is an input to the bid, not something the schedule produces. Licence classifications come from the CSLB and the scope of each subcontract. And the overtime schedule is a labour-planning matter governed by the wage and hour rules.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report